How to set up a drawing register and revision control

A drawing register lists every drawing with its current revision and status. Here is what to record, how to label revisions and how to keep it accurate.

Updated 1 November 2026.

The short answer

A drawing register is one list of every drawing on the project with its current revision, status and issue history. Revision control is the discipline of changing that list only when a new revision is issued, marking the old one superseded, and issuing only from the register. Set both up before the first issue, because fixing them mid-project is much harder.

What to record for every drawing

At a minimum: the drawing number, title, discipline, current revision, status, the date of the current revision, and who it has been issued to and when.

How to label revisions

Pick one convention at the start and apply it to every drawing. Some projects use letters (A, B, C) or numbers (0, 1, 2). Others follow ISO 19650, where preliminary revisions are P01, P02 and contractual revisions are C01, C02. Put the convention in the contract documents, so consultants and subcontractors use the same one.

How to set it up

  1. Agree the numbering and revision convention with the design team before the first issue.
  2. Build the register from the drawings you hold, with one row per drawing and one current revision.
  3. Add a status for each drawing, such as For Information, For Review or For Construction, and treat only For Construction drawings as buildable.
  4. Mark every earlier revision as superseded when a new one arrives, and keep it linked to the new one.
  5. Issue drawings only from the register, under a transmittal that lists the exact revisions sent.
  6. Check the register against what consultants have issued at least weekly, and fix differences straight away.

Common mistakes

The common mistakes are overwriting a file instead of issuing a new revision, letting two copies of the register circulate, treating the title block revision and the register revision as separate things, and not recording who received what.

How Tracta handles it

Tracta builds the register from your uploaded drawings, and you can export it to CSV. The earlier revision is marked superseded and stays linked behind the new one, and the file on a revision that has been sent can't be replaced.

A list of every drawing on a project with its number, title, current revision, status and date. It tells everyone which drawing is current.

The register shows the state of every drawing now. A transmittal records one issue: which revisions went to whom and when.

Yes, and many builders do. It works while one person updates it and nobody issues drawings from outside it. It struggles when several people edit it and nothing ties it to what was actually sent.

Every time a new revision is received or issued, not in batches. A register that lags behind reality is the usual cause of builds from old revisions.